35th Ave NE Project: Construction Update (5/7/19)

Overview of upcoming work as of May 7, 2019

Night work for final striping on 35th Ave NE begins tonight, Tuesday, May 7 and continues for the next several weeks

Due to the anticipated daytime temperatures in the upper 70s and 80s for the next several weeks, our contractor needs to install final striping on 35th Ave NE at night. Higher temperatures can cause new paint to take longer to cure and is harder to clean up if a vehicle drives through it. Crews will begin work between NE 47th and 75th streets. Once complete, crews will continue working at night between NE 75th and 91st streets.

We are working to minimize impacts wherever feasible and 35th will remain open with one lane in each direction during the work. Please read below for what to expect while striping takes place: 

  • Nighttime hours: 7 PM to 7 AM, Monday through Friday
  • 1 lane of traffic in both directions will be maintained at all times: Uniformed police officers (UPOs) and flaggers will direct traffic around the work area
  • Parking will be restricted along the corridor to maintain a safe work area
  • Noise and vibrations during final striping installation at night are expected to be slightly louder than typical traffic but not as loud as nighttime paving. 
  • All sidewalks will remain open for people walking 

If you have questions or concerns about the work, please contact our project information line, 206-512-3950, as soon as possible and we will do our best to minimize impacts whenever feasible.

Driveways will remain accessible, but you may experience intermittent delays while paint is drying:

Uniformed police officers (UPOs) and flaggers may re-direct you to avoid driving on fresh paint when trying to access a driveway. Fresh paint that has been driven on is difficult to clean up and harmful to vehicles.

If you have concerns about accessing your driveway during nighttime work, please park on side streets and walk to your residence or business.

25th Ave NE Paving Project
Paving for the 25th Ave NE Paving Project is now complete! Please see our construction email update archive for more information about what to expect for the remaining work. 

Stay informed

You can find more background about this project on our webpage. Please forward this email to those you think will be interested or share this link to sign up to receive construction updates by email. If you have questions, please contact us at 35thAvePaving@seattle.gov or 206-512-3950.

Contact
35th Ave NE Project Outreach Team
Seattle Department of Transportation
Construction information line: (206) 512-3950
35thAvePaving@seattle.gov
www.seattle.gov/transportation/35thNEpaving.htm

For translation services, please call (206) 512-3950.
Servicios de traducción e interpretación disponibles bajo petición (206) 512-3950.
Matutulungan ka naming maintindihan kung hihingi kang tulong (206) 512-3950.
요청하시면 번역이나 통역을 제공해드립니다 (206) 512-3950.
Dịch và thông dịch viên sẵn sàng nếu có sự yêu cầu (206) 512-3950.
Haddii aad dooneyso turjubeen fadlen wac (206) 512-3950.
Tajaajiliwwan hiikkaa fi turjumaanaa yoo karaa (206) 512-3950 tiin gaafattan jira. 
በ (206) 512-3950 ጥያቄ በማቅረብ የትርጉም እና አስተርጓሚ አገልግሎቶች ይቀርባሉ፡፡
ብዝቐርብ ሕቶ መሰረት ግልጋሎት ትርጉም ኣሎ እዩ (206) 512-3950::

Nathan Hale High School 2019 Spring Edible & Ornamental Plant Sale – May 10/11

Dear Friends of Nathan Hale’s Horticulture Program—

Our 2019 Spring Edible and Ornamental Plant Sale is right around the corner!

We are having a special Early Bird Event on May 10 from 4 -8 pm, and a public sale on May 11 from 9 am to 3 pm.  Tickets for the Early Bird Event are available on the Brown Paper Tickets website.  Get your tickets soon—quantities are limited!

We welcome gardeners from all over the city and beyond to come and enjoy Nathan Hale Urban Farm, our students and our well-priced plants!  Please visit our website to get our plant inventory list, driving directions and learn more about Nathan Hale Urban Farm:  nathanhaleurbanfarm.org   You can also learn more about our program by watching this recent spot on KIRO TV with reporter Deborah Horne.

We hope you will join us on May 10 and 11 for the sale.  We would really appreciate it if you would forward this message to your plant-loving colleagues, friends and family members.

Location: Greenhouse/Urban Farm are north of  Jane Addams Middle School parking lot.  Entrance  at 113th  St. and 31st  Ave, NE

Thank you,

Jessica Torvik, President

Friends of Nathan Hale Horticulture and Urban Farm

Grow Hale

Closure on the Burke-Gilman Trail May 6

Trail closed between 42nd Pl NE and 40th Ave NE

A contractor working with King County Parks will be removing six hazardous trees leaning  out along the trail. The project is expected to take one full day to complete and will begin at 9 a.m. on Monday, May 6, 2019 and be complete by 7 p.m.

Trail users may opt to use Riviera Place NE as a bypass for the duration of the closure. We ask that all trail users please obey all posted trail closure signs as the trail is narrow and the edge drops off quickly around the work site.

BGT tree removal area

Please call 206-477-4527 or email parksinfo@kingcounty.gov with any questions or concerns.

35th Ave NE Project: Construction Update (04/18/19)

Paving on 35th Ave NE between NE 75th and NE 89th streets has been postponed andis now scheduled to take place starting at 6 PM on Friday, April 26. Paving activities may continue as late as 5 pm on Saturday, April 27 based on site conditions. This work is weather-dependent and could change. 

Overview of upcoming work as of April 18, 2019

Zone C (between NE 75th and NE 89th streets):

Crews continued preparing for final paving this week and made great progress by finishing all panel repairs on 35th Ave NE. Next week, people will continue to see crews in the project area conducting maintenance and electrical work prior to paving. Traffic control and parking restrictions will remain in place for your safety and the safety of our crews.

What to expect prior to paving on April 26:

  • Typical work hours: Monday – Saturday 7 AM to 7 PM
  • Northbound detour: Northbound traffic will be detoured to Sand Point Way NE between NE 75th and NE 95th streets. 
    • 35th will be fully open between NE 65th and 75th streets. However, trucks and other drivers that are traveling through the area may use eastbound NE 65th St to Sand Point Way NE as a detour route.

Please follow detour signs for everyone’s safety. During previous detours, we’ve heard concerns from your neighbors about cut-through traffic on side streets. Please follow the posted detour route and if you must use side streets to reach your home, please drive slowly and watch out for one another.

  • Driveway access: Crews may need to partially block driveways to accommodate safe work zones near existing driveways 
    • If a full driveway closure is needed, we will notify businesses and residents in advance
  • Limited turns to/from side streets on 35th Ave NE between NE 75th and 89th streets: Side street access will be limited to establish a safe work area
  • Parking restrictions: Street parking will be closed 24/7 on both sides of 35th Ave NE between NE 73rd and NE 89th streets until construction is finished 
    • Please read the restrictions listed on the no parking signs for details to avoid being ticketed or towed
  • Temporary bus stop closures and reroutes: Get the latest information at King County Metro Alerts

Detour map April 18 – 25

What to expect during nighttime paving, scheduled for Friday, April 26:

  • Nighttime paving hours: Starting approximately 6 PM on Friday, April 26 through as late as 5 PM on Saturday, April 27 (based on site conditions and work progress)
  • 35th Ave NE will be fully closed to vehicle traffic between NE 75th and NE 90th streets
    • Vehicles will be detoured at NE 65th and NE 95th streets to Sand Point Way NE 
    • Local access only will be maintained for residents and businesses from NE 65th to NE 75th and from NE 90th to NE 95th 
  • Residents and businesses between 75th and 90th streets will not have access to their driveways on 35th Ave NE during nighttime paving
    • Please park on side streets before 6 PM on Friday, April 26 
  • All sidewalks will remain open. People walking will be able to cross 35th Ave NE at NE 75th St and NE 90th St
    • Please do not walk across 35th Ave NE during paving. Asphalt and tar are very hot and harmful to people and animals
  • Bus stops may be temporarily closed and buses may be rerouted during paving: get the latest information at King County Metro Alerts
  • Please note, paving is weather dependent and may be rescheduled 

If you have access concerns, please contact our project information line, 206-512-3950, as soon as possible and we will do our best to minimize impacts during nighttime paving.

Nighttime paving detour map: April 26 – 27

25th Ave NE Paving Project
We’re coordinating with the 25th Ave NE Paving Project
 as they complete final paving. During nighttime paving on 25th Ave NE, northbound traffic from 25th Ave NE will be detoured to 35th Ave NE south of NE 65th St. For the latest construction information, please see our construction email update archive

35TH AVE NE PROJECT DROP-IN SESSION
We’re hosting a drop-in session where you can learn more about the new design and how 35th Ave NE will operate in the future. This will be an open house event with no formal presentation. Please join us at whatever time is most convenient for you. We’ll have information boards and staff available to answer your questions. Event details below:

Wednesday, April 243 – 7 PM
Ravenna-Eckstein Community Center, 6535 Ravenna Ave NE, Seattle


Translation services and accommodations available if requested one week in advance. Can’t attend the event? Visit our webpage for additional information. 

Stay informed

We know that construction projects like this can be disruptive and we appreciate those of you that reached out to us during the winter with questions and concerns. Our goal is to work as efficiently as possible to complete the remaining construction activities. Thank you for your patience. 

You can find more background about this project on our webpage. Please forward this email to those you think will be interested or share this link to sign up to receive construction updates by email. If you have questions, please contact us at 35thAvePaving@seattle.gov or 206-512-3950.

Contact
35th Ave NE Project Outreach Team
Seattle Department of Transportation
Construction information line: (206) 512-3950
35thAvePaving@seattle.gov
www.seattle.gov/transportation/35thNEpaving.htm

35th Ave NE Project: Construction Update (04/05/19)

Construction on 35th Ave NE to resume on April 8
Crews plan to restart construction for the 35th Ave NE Project between NE 75th and NE 89th streets on April 8. Please read below for detailed information about upcoming work.

Overview of upcoming work as of April 5, 2019
Zone C (between NE 75th and NE 89th streets):

On Monday, April 8, crews plan to begin grinding the top several inches of asphalt to prepare for paving. This work is expected to take approximately 2-3 days to complete. Once crews finish grinding, we will use street sweepers to clean-up the work area. Then we will make any additional repairs to the street base and upgrade the remaining curb ramps at NE 75th St and NE 89th St.  

During grinding and base repair work, you can expect the following: 

  • NEW: Northbound detour: We have received an updated plan from the contractor and wanted to share it with the community prior to work starting. On April 8, 35th Ave NE will be open to southbound traffic only between NE 75th and NE 95th streets. Northbound traffic will be detoured to Sand Point Way NE between NE 75th and NE 95th streets. 
    • Trucks and other drivers that are traveling through the area may also use eastbound NE 65th St to Sand Point Way NE as a detour route  
    • The detour provides space on 35th for crews to work safely . The detour route to Sand Point Way NE is necessary because of the limited number of arterial streets in this area. It is also one of the few routes that accommodates truck traffic.
  • Temporary driveway closures for up to 1 hour as the grinding machine passes

Please follow detour signs for everyone’s safety. During previous detours, we’ve heard concerns from your neighbors about cut-through traffic on side streets. Please follow the posted detour route and if you must use side streets to reach your home, please drive slowly and watch out for one another.

  • Parking restrictions: Street parking will be closed on both sides of the street, 24/7 until construction is finished, between NE 75th and NE 89th streets
    • Please read the restrictions listed on the no parking signs for details to avoid being ticketed or towed
  • Limited turns to / from side streets and driveways on 35th Ave NE between NE 75th and 89th streets: Side street access will be limited to establish a safe work area
  • Temporary bus stop closures and reroutes: Get the latest information at King County Metro Alerts
  • Typical work hours: Weekdays from 7 AM – 7 PM
Detour map

25th Ave NE Paving Project
We’re coordinating with the 25th Ave NE Paving Project as they plan for final paving overnight in early April. During nighttime paving on 25th Ave NE, northbound traffic from 25th Ave NE will be detoured to 35th Ave NE south of NE 65th St. For the latest construction information, please see our construction email update archive

A new design for 35th Ave NE 
Last month, we announced a new design for the 35th Ave NE Project. If you would like to learn more about the how the design has changed, please visit our project webpage
 or read our blog post.
Stay informed
We know that construction projects like this can be disruptive and we appreciate those of you that reached out to us during the winter with questions and concerns. Our goal is to work as efficiently as possible to complete the remaining construction activities. Thank you for your patience. 

You can find more background about this project on our webpage. Please forward this email to those you think will be interested or share this link to sign up to receive construction updates by email. If you have questions, please contact us at 35thAvePaving@seattle.gov or 206-512-3950.
Contact
35th Ave NE Project Outreach Team
Seattle Department of Transportation
Construction information line: (206) 512-3950
35thAvePaving@seattle.gov
www.seattle.gov/transportation/35thNEpaving.htm