35th Ave NE Project: Construction Update (5/7/19)

Overview of upcoming work as of May 7, 2019

Night work for final striping on 35th Ave NE begins tonight, Tuesday, May 7 and continues for the next several weeks

Due to the anticipated daytime temperatures in the upper 70s and 80s for the next several weeks, our contractor needs to install final striping on 35th Ave NE at night. Higher temperatures can cause new paint to take longer to cure and is harder to clean up if a vehicle drives through it. Crews will begin work between NE 47th and 75th streets. Once complete, crews will continue working at night between NE 75th and 91st streets.

We are working to minimize impacts wherever feasible and 35th will remain open with one lane in each direction during the work. Please read below for what to expect while striping takes place: 

  • Nighttime hours: 7 PM to 7 AM, Monday through Friday
  • 1 lane of traffic in both directions will be maintained at all times: Uniformed police officers (UPOs) and flaggers will direct traffic around the work area
  • Parking will be restricted along the corridor to maintain a safe work area
  • Noise and vibrations during final striping installation at night are expected to be slightly louder than typical traffic but not as loud as nighttime paving. 
  • All sidewalks will remain open for people walking 

If you have questions or concerns about the work, please contact our project information line, 206-512-3950, as soon as possible and we will do our best to minimize impacts whenever feasible.

Driveways will remain accessible, but you may experience intermittent delays while paint is drying:

Uniformed police officers (UPOs) and flaggers may re-direct you to avoid driving on fresh paint when trying to access a driveway. Fresh paint that has been driven on is difficult to clean up and harmful to vehicles.

If you have concerns about accessing your driveway during nighttime work, please park on side streets and walk to your residence or business.

25th Ave NE Paving Project
Paving for the 25th Ave NE Paving Project is now complete! Please see our construction email update archive for more information about what to expect for the remaining work. 

Stay informed

You can find more background about this project on our webpage. Please forward this email to those you think will be interested or share this link to sign up to receive construction updates by email. If you have questions, please contact us at 35thAvePaving@seattle.gov or 206-512-3950.

Contact
35th Ave NE Project Outreach Team
Seattle Department of Transportation
Construction information line: (206) 512-3950
35thAvePaving@seattle.gov
www.seattle.gov/transportation/35thNEpaving.htm

For translation services, please call (206) 512-3950.
Servicios de traducción e interpretación disponibles bajo petición (206) 512-3950.
Matutulungan ka naming maintindihan kung hihingi kang tulong (206) 512-3950.
요청하시면 번역이나 통역을 제공해드립니다 (206) 512-3950.
Dịch và thông dịch viên sẵn sàng nếu có sự yêu cầu (206) 512-3950.
Haddii aad dooneyso turjubeen fadlen wac (206) 512-3950.
Tajaajiliwwan hiikkaa fi turjumaanaa yoo karaa (206) 512-3950 tiin gaafattan jira. 
በ (206) 512-3950 ጥያቄ በማቅረብ የትርጉም እና አስተርጓሚ አገልግሎቶች ይቀርባሉ፡፡
ብዝቐርብ ሕቶ መሰረት ግልጋሎት ትርጉም ኣሎ እዩ (206) 512-3950::

Community Prioritization for ‘Neighborhood Street Fund’

Now through February 22nd residents are able to prioritize transportation related projects through the Seattle Department of Neighborhoods (DoN) ‘Neighborhood Street Fund’ (NSF).  Meadowbrook needs your help to ensure our proposed projects (proposals) rise to the top of this competitive prioritization process. Funds for these projects will range from between 100K and One million dollars compared to the smaller Your Voice, Your Choice projects which top out at $90K.

Community Prioritization phase of Neighborhood Street Fund 2019-2021 cycle is now open! Tell us what street improvements your community needs most by scoring projects proposed by neighbors in your district now through February 22. The highest-scored projects will proceed to the voting phase in Spring.

How to score:

  • Online: prioritize projects and participate in an online dialogue with your neighbors without leaving your home! 
  • In-person: attend a 90-minute Community Prioritization Meeting in your district. Meetings will include presentations by SDOT staff of each project proposed in your district. (Please note that presentations will begin promptly at the meeting start, so arrive on time! To request interpretation and or another accommodation, please contact us at: nsf@seattle.gov or (206) 733-9361 before the meeting date. Due the bad weather, the first round of meetings for District 5 have been canceled, but they may be rescheduled at another date. This is to be determined by DoN.

The Meadowbrook Sidewalk Committee has 6 priority projects within the boundaries of Meadowbrook that we need you to support as high priority

  1. #203, Construct a curbed, asphalt walkway on the south side of Ne 115th between 35th and 40th Ave Ne;
  2. #205, Complete asphalt walkway on Ne 100th from near Ravenna to the entrance of Seattle Waldorf School;
  3. #016, Add school zone ticketing cameras on Ne 115th between 30th and 34 Aves Ne;
  4. #177, Install a sidewalk on the south side of Ne 95th between 30th and 32nd Aves NE;
  5. 170, Construct an asphalt walkway on west side of 39th Ave Ne from crosswalk on Ne 108th to trail into Meadowbrook Pond area (benefits John Rogers Elementary)
  6. #174, Install speed reduction treatments on Sand Point Way between 95th and 125th Ave Ne;

Visit http://www.seattle.gov/transportation/projects-and-programs/programs/neighborhood-street-fund/projects-map  to score online or check the meeting schedule!

Thank you for your participation in the NSF Program. 

Neighborhood Street Fund-FAQ http://www.seattle.gov/Documents/Departments/SDOT/NSF/2018/NSF_2019FAQ_20181019.pdf